The construction permit for a solar PV power plant with power capacity of up to 200kW is issued on the basis of an approved technical project. This is possible only after approval of the project by the EDC and the Municipal Administration of both the structural part and the electrical part of the designs. The process from the approval of the project to the issuance of the construction permit takes about one calendar month. The steps from the administrative process to the preparation of a technical project, including obtaining a position document for connecting to the grid by the EDC, in turn, take 1-2 months. Variations are possible depending on the specific requirements and deadlines of the local municipal administration and the local EDC.