Legislative process
Own consumption up to 20kW
1 week
1. Preliminary research
Preliminary study of the conditions for the construction of a power plant, preparation of a conceptual project, preliminary offer and analysis of the investment.
1 week
2. Construction Notice to ERP
We assist customers with the preparation of the notification to the local ERP, which includes technical data for the plant.
issued upon submission of a Notice
3. Additional Agreement
Based on a submitted request, EPR issues an Additional Agreement to an existing access and transmission contract.
The Agreement includes information about;
The Agreement includes information about;
- the authorized power for the construction of a FPP
- technical requirements for the connection scheme of the energy object to the customer's electrical system
issued upon submission of a Notice
1 month
4. Project solution
(Art. 151, Para. 10) Pursuant to an additional agreement and site inspection, the designers of "EU-3" prepare a design decision.
The project solution part "Electrical" and part "Constructive" includes drawings, diagrams, calculations, technical specifications and installation instructions, guaranteeing safe operation and protection against the return of electricity, energy to the network.
The project solution part "Electrical" and part "Constructive" includes drawings, diagrams, calculations, technical specifications and installation instructions, guaranteeing safe operation and protection against the return of electricity, energy to the network.
1 month
5. Notice to the Chief Architect of the Municipal Administration
Within 14 days before the start of construction, the investor submits a notification describing the power of the installation and its location, and applies the design solution prepared by "EU-3".
1 week
6. Contract for the construction of FEC
On the basis of technical documentation and an Additional Agreement with the ERP, a contract is drawn up and concluded between the client and "ES-3" for the supply of equipment, construction and commissioning of the FPP.
1 week
according to contract
7. Delivery of equipment and construction of a power plant
At "ES-3" we maintain stocks of all necessary components and plan the implementation of our sites so that at the moment of signing a contract with us, the equipment for your PEP will be available in our warehouse.
according to contract
8. Installation done notification
After completion of the construction, the client submits a Notification to the ERP and a Declaration to the Chief Architect that the installation has been energized and has been completed according to the technical documentation.